2026 Capital Improvements Bond
2026 Capital Improvements Bond
Building a Stronger Foundation for the Future_1778679943.jpg)
On May 19, residents of the Pearl River School District approved a $61.4 million bond to fund comprehensive renovations to essential infrastructure in all school buildings. The project scope addresses critical needs identified in the District’s NYSED Building Conditions Survey and priorities voiced by families, students and staff in our Capital Project Community Survey.
A stronger foundation for student success starts with healthy, safe and comfortable learning environments.
District-wide School Renovations
- New heating, ventilation and air conditioning (HVAC) systems, including upgrades to:
- All elementary school multipurpose spaces
- Pearl River Middle School cafeteria and gymnasium
- Pearl River High School auditorium and gymnasium
- Boiler replacement at each school
- New ceilings and LED lighting in selected areas of each school
- Roof removal and replacement at each school
District-wide Safety and Security Upgrades (All Schools)
- Lockdown system integration and installation of notification strobes
- Exterior access control enhancements
- Interior door replacements and hardware upgrades
- Fire alarm system upgrades and expansion of coverage
Improvements to Support Student Wellness and Programming
- Playground resurfacing and equipment upgrades to the Blauvelt Road playground at Evans Park Elementary School and rear playgrounds at Lincoln Avenue Elementary School and Franklin Avenue Elementary School
- Renovation of PRMS library media center, computer room and technology classroom; sink, faucet and casework replacement in science classrooms; athletic field drainage improvements and new irrigation system
- Renovation of PRHS locker and team rooms; gym floors, bleachers, basketball goals and divider walls; turfing of and drainage upgrades to softball, baseball and practice fields; and addition of visitor bleachers on multipurpose field
PROJECT COST
$63.6 million Total Project Budget
- $2.2 million Capital Reserve Funds
$61.4 million Total Bond*
--
*$373 annually
Estimated additional cost to residents with a home assessed at $200,000
CONSTRUCTION PERIOD
[IMAGE]
Summer 2027- Fall 2029
PROJECT TIMELINE
May 19, 2026: Bond for 2026 Capital Improvement Projects approved by Pearl River community.
June 2026: CSARCH develops preliminary phasing scheduling for projects. Request for Proposal (RFP) for Construction Management (CM) firm.
July 2026: RFP issued, review responses.
August 6, 2026: CM interviews and selection of finalists.
August 11, 2026: The Palombo Group appointed as CM.
September 3, 2026: Kick Off Meeting with CSARCH, The Palombo Group, Pearl River District Administration. Phasing schedule of projects reviewed and approved by The Palombo Group and District Administration.
October through December is the design phase for the project leading up to submission of plans to NYSED for their approval.
Capital Improvements Bond Video
PRHS Project Renderings
-
PRHS Baseball & Softball Practice Fields -
PRHS Boys Team Room -
PRHS Girls Team Room -
PRHS Girls Locker Room
PRMS Project Renderings
-
PRMS Library -
PRMS Library -
PRMS Library -
PRMS Tech Room
Elementary Playground Project Renderings
-
Evans Park Playground -
Franklin Avenue Playground -
Lincoln Avenue Playground